You are here:Home / Featured /Muskrat Falls project delayed again

Muskrat Falls project delayed again

Nalcor blames COVID-19 for failing to meet contracted schedule of delivery of power to Nova Scotia Power, but there are also problems with software. As a result, Nova Scotia likely won't meet its renewable energy targets.

April 18, 2020ByJennifer Henderson2 Comments

A Nalcor Energy schematic of the Muskrat Falls project.

Hydroelectricity expected to flow to Nova Scotia from Labrador to reduce dependence on coal-fired plants has been delayed once again. Inits quarterly reportto the Utilities and Review Board, NS Power Maritime Link (NSPML) says the builder of the Muskrat Falls project is experiencing pandemic-related delays.

On March 17, Nalcor (the Newfoundland utility building the Muskrat Falls dam) paused construction at its Muskrat Falls and Labrador Island Link sites due to physical distancing restrictions related to the virus. Nalcor has declared a Force Majeure. “Force Majeure” is a clause in contracts which releases a company from its legal obligations when an extraordinary unforeseen event hits, such as a pandemic or a major hurricane.

June 1, 2020 was the date Nova Scotia was supposed to take delivery via the Maritime Link undersea cable between Cape Breton and Newfoundland. It’s been in place and operational since January 2018. The 35-year, fixed-price contract between NS Power and Nalcor is supposed to deliver enough renewable energy to meet 20% of the demand here in Nova Scotia.

Nova Scotia Power (NSP) was also counting on Muskrat Falls to comply with legislated renewable energy targets that require 40% of electricity to be generated from green sources by the end of 2020. The province generated 30% from renewables in 2019.

GE Software a major glitch

Muskrat Falls is now two years late and at least $6 billion over budget. Prior to the COVID-19 outbreak, Nalcor was projecting completion for July 2020. It says the Muskrat Falls project is 98% complete.

In its April 15 update to the regulator, NSP says the cable system delivering hydro from Muskrat Falls in Labrador to Newfoundland — known as the Labrador Island Link (LIL) — is 99% complete.

But the unresolved issue is the software needed to operate and control the transmission over that Link is still in development and testing. It was supposed to be ready last August but General Electric, which is supplying the software, ran into a major problem.

“Since the pause of work at the construction sites in Newfoundland, Nalcor and its Contractor, GE, have been able to safely continue development and testing of the interim Protections & Controls (P&C) Software needed for operations and are nearing factory acceptance testing,” reads the quarterly report from NSPML.

“Due to the unpredictable nature of the COVID-19 pandemic, Nalcor is currently unable to provide an updated schedule for LIL or the generation project at Muskrat Falls and intends to wait until there is greater certainty to update its Integrated Project Schedule.”

Where that leaves the customer, Nova Scotia Power, is uncertain. What that means for ratepayers here is that the utility is now searching for a large chunk of replacement power that may cost more to buy and affect the cost of electricity next year.

“As with many businesses and project sites across the country, implications from COVID-19 are being felt and we are no different,” said Jacqueline Foster, communications advisor with NSP. “Given this news, we will continue to explore economical options to achieve the same amount of renewable energy. As always, we are committed to finding an affordable solution for our customers. The Maritime Link provides long-term strategic benefit to electricity customers in Nova Scotia, Newfoundland & Labrador, and the entire Atlantic region.”

No date has been given when work will resume on the massive hydroelectric project. The April 15 document says “Nalcor has expressed its desire to return to the site as soon as it safe for employees, contractors, and associated communities.”


The Halifax Examiner is an advertising-free, subscriber-supported news site. Your subscription makes this work possible;please subscribe.

Some people have asked that we additionally allow for one-time donations from readers, so we’ve created that opportunity, via the PayPal button below. We also accept e-transfers, cheques, and donations with your credit card; please contact iris “at” halifaxexaminer “dot” ca for details.

Thank you!




Filed Under:Featured,NewsTagged With:COVID-19,General Electric (GE),Jacqueline Foster,Labrador Island Link (LIL),Muskrat Falls,Nalcor,Nova Scotia Power (NSP)

AboutJennifer Henderson

Jennifer Henderson is a freelance journalist and retired CBC News reporter.email:[email protected]

Comments

  1. chardonsays

    April 20, 2020 at 12:18 pm

    I read somewhere a year or so ago that many (if not most) mega-projects end up costing much more than initially projected. All the more reason to hit the pause button on the QE-2 expansion project, and do a thorough evaluation of this project – and to involve the public.

    Log in to Reply

Trackbacks

  1. Good Sunday Morning – August 23 – Elizabeth May says:
    February 3, 2021 at 12:31 am

    […] of red ink is a lot like Site C. The N-L disastrous dam is Muskrat Falls in Labrador. It is now two years late and $6 billion over budget. And just as the BC government wants to do here, N-L is forbidding any […]

    Log in to Reply

Leave a ReplyCancel reply

You must belogged into post a comment.

PRICED OUT

A collage of various housing options in HRM, including co-ops, apartment buildings, shelters, and tents
PRICED OUT is the Examiner’s investigative reporting project focused on the housing crisis.

你可以了解这个项目,包括我们如何re asking readers to direct our reporting, our published articles, and what we’re working on, on thePRICED OUT homepage.

The Tideline, with Tara Thorne

Duane Jones, a Black man in a black t-shirt with a tiger graphic on the front. He's standing in front of a chain link fence on a summer day, and behind him you can see green trees blurred in the background.
Episode 61 of The Tideline, with Tara Thorne, is published.

Art Pays Me’s founder Duane Jones kicks off the new year with hope and advice as he details his journey from failed accounting student to founder of Halifax’s favourite streetwear line. He beams into the show to chat about his years at NSCAD, what happened when he realized his talent was being exploited, and how he turned that into a brand that demonstrates his personal ethos. Plus he and Tara discuss the series finale of Insecure, and whether Issa’s choice was the right one.

Listen to the full episode here.

Check out some of the past episodeshere.

Subscribe to the podcast to get episodes automatically downloaded to your device — there’s agreat instructional article here.Email Suzannefor help.

You canreach Tara here.

Uncover: Dead Wrong

1995年,布伦达方式背后被残忍地谋杀了Dartmouth apartment building. In 1999, Glen Assoun was found guilty of the murder. He served 17 years in prison, but steadfastly maintained his innocence. In 2019, Glen Assoun was fully exonerated.

Halifax Examiner founder and investigative journalist Tim Bousquet has followed the story of Glen Assoun's wrongful conviction for over five years. Now, Bousquet tells that story as host of Season 7 of the CBC podcast series Uncover: Dead Wrong.

Click here to go to listen to the podcast, or search for CBC Uncover on Apple podcasts, Spotify, or any other podcast aggregator.

About the Halifax Examiner

Examiner folkThe Halifax Examiner was founded by investigative reporter Tim Bousquet, and now includes a growing collection of writers, contributors, and staff. Left to right: Joan Baxter, Stephen Kimber, Linda Pannozzo, Erica Butler, Jennifer Henderson, Iris the Amazing, Tim Bousquet, Evelyn C. White, El Jones, Philip MoscovitchMore about the Examiner.

Sign up for email notification

Sign up to receive email notification when we publish new Morning Files and Weekend Files. Note: signing up for this email is NOT the same as subscribing to the Halifax Examiner. To subscribe,click here.

Recent posts

  • Three Nova Scotian men have died from COVID-19; 59 people now hospitalized with the diseaseJanuary 10, 2022
  • What is the pandemic doing to sports — and other — reporting?January 10, 2022
  • 837 new cases of COVID-19 announced in Nova Scotia on Sunday, Jan. 9January 9, 2022
  • Omicron (less than) one month laterJanuary 9, 2022
  • 1,145 new cases of COVID-19 announced in Nova Scotia on Saturday, Jan. 8January 8, 2022

Commenting policy

All comments on the Halifax Examiner are subject to our commenting policy. You can view our commenting policyhere.

Copyright © 2022